The Cedar Glen Observatory

Observatory Construction
Home
Du Bois Aviation
Weather/Webcam
News
Observatory Automation
Observatory Construction
Observatory Equipment
Old Roll-Off Observatory
Old Observatory Equipment
Apogee Alta U6 MPO/Images
DSI Pro B&W Images
Old 1004X B&W CCD Images
Old House Photos
Contact
The house and observatory burned to the ground along with 324 other homes on October 29th 2003. Building of the new house started in September of 2004. Lake Arrowhead Building Company is the contractor.

As it looked November 6th, 2003.

dsc00513.jpg

04/05/2004 after cleanup... The county did not issue ANY building permits for six months....

dscf0018.jpg

09/18/2004, foundation footing being dug. We had to dig some footings 7' deep!

dscf0263.jpg

10/18/2004, concrete forms in place and retaining walls complete. The pier footing contains 6.6 yards of concrete which weights 16,200lbs.

dscf0292.jpg

11/01/2004, concrete complete. Total of 73 yards or 177,000lbs of concrete (90 tons).

dscf0308.jpg

11/12/2004, framing begins. Pier installed. The telescope pier is 16' in dia., 20 feet tall, and weighs 1200lbs. It is attached to the concrete base via four 7/8-12 studs that were welded to a rebar cage.  The bottom ten feet will be filled with sand and the rest with 2-part foam. This is earthquake country... having a large mass at the top is not a good idea....

dscf0309.jpg

12/02/2004, framing continues....

dscf0325.jpg

01/17/2005 framing continues... North second floor exterior wall ready to go up. The south wall was already up, but blew over and was destroyed. The pier is isolated from the house (does not touch).

dscf0351.jpg

02/04/2005. 2nd floor exterior walls up. Roof framing begun.

dscf0362.jpg

02/15/2005. Roof complete. Framing of observatory is next....

dscf0371.jpg

02/28/2005. Framing of observatory begins. The observatory is 7'10" in dia., and 13' tall. A 2.5m Observadome will be placed on top. A internal spiral staircase leads from the control room on the second floor to the top of the observatory.

dscf0410.jpg

03/05/2005. 2.5m Observadome in place. Next will come cedar shingles then the dome skirt.

dscf0421.jpg

03/21/2005, Cedar shingles in place. The dome skirt will be installed after the house in painted.

dscf0515.jpg

05/13/2005. Cedar shingles stained, house painted...

dscf0526.jpg

06/02/2005. Roof complete, still need to install skirt...

dscf0543.jpg

07/17/2005. Skirt installed.

dscf0641.jpg

08/23/2005. Almost complete. Scope installed, need to finish interior paneling.

dscf0672.jpg

Lake Arrowhead Building Company can be found here.

All images on this site are subject to copyright and must not be reproduced without permission from the Cedar Glen Observatory